Task 1003 is defined as what in scheduling logic?

Explanation:
In scheduling, a task that cannot start until another finishes shows a dependency where the current task has a predecessor. This is a finish-to-start relationship: the predecessor must complete before the successor can begin. So Task 1003 being defined as unable to start until Task 1002 finishes means 1003 is dependent on 1002 and is a successor to it. The other statements describe different scenarios: a fixed 5-day delay implies a lag not tied to a specific predecessor, a task with no predecessors is independent, and starting anytime means there are no constraints.

In scheduling, a task that cannot start until another finishes shows a dependency where the current task has a predecessor. This is a finish-to-start relationship: the predecessor must complete before the successor can begin. So Task 1003 being defined as unable to start until Task 1002 finishes means 1003 is dependent on 1002 and is a successor to it.

The other statements describe different scenarios: a fixed 5-day delay implies a lag not tied to a specific predecessor, a task with no predecessors is independent, and starting anytime means there are no constraints.